INDUSTRY

Price Contact
Site Binh Dinh Province
Scale 2000 m2
Item Construction
Time 2012

Construction of cement silo of Vicem Hai Van factory, Binh Dinh province.

Other products

HYDROPOWER PLANT

Dark'Tih Hydropower Plant is a project invested by Construction Corporation 1 (CC1) in Gia Nghia town, Dak Nong province, with a total investment of over 5,000 billion VND.
Technical scale of the Project:
- Dark'tih hydropower project is exploited according to the scheme of 2 levels (Upstairs and Lower Levels) including 02 units H1 & H2 belonging to the Upper Tier plant with a capacity of 41MW each and 02 H3 & H2 units. H4 belongs to the Lower Tier factory with a capacity of 31MW each.
- Truong Thinh Investment Construction & Trading Joint Stock Company is the construction unit of the items: Lower level factory, upper level spillway, distribution station, part of culvert and operating road...

PREFABRICATED BUILDING

Pre-engineered steel buildings are houses made of steel structures, fabricated and installed according to pre-specified architectural and technical drawings. The process of making the finished product (with a combination of inspection and quality control steps) goes through 3 main stages:

- Design

- Components processing

- Installation at the site.

The entire steel structure can be produced synchronously and then delivered to the construction site in a relatively short time.

If a project needs cost savings, fast erection, absolute quality control and sustainability, pre-engineered steel buildings are the best choice.

Produce and process the metal structure according to standard or non-standard

With the factory area 25,000 m2 and modern technology including:

- 3 in 1 horizontal welding machine
- King post welding machine
- CNC 3D welding machine
- Shot blasting machine

We can definitely produce the steel structure according to standard or non-standard

IRRIGATION

Truong Thinh participated in the construction of 05 bidding packages, the workload includes concreting the soil canal system and renovating and renovating the operating road along the canal. Grade 1 red gravel road in Duong Minh Chau district. Road along the canal side of grade 1 before construction of road surface structure.

Level 1 water canal system and operating roads on both sides of the canal of Tay Ninh PMU oil irrigation system.
0/5
(0 nhận xét)
  • 0% | 0 comments
  • 0% | 0 comments
  • 0% | 0 comments
  • 0% | 0 comments
  • 0% | 0 comments

Chia sẻ nhận xét về sản phẩm

Gửi nhận xét
GỬI ĐÁNH GIÁ CỦA BẠN
Đánh giá
Gửi

E-Brochure

For more details about the company, products and projects, please download our E-Brochure here. 
Contact for consultation. Thank you. 
content to consult